This multi-year bridge project was completed in 2023. PCiRoads was subcontracted through Ames Construction to pour Micro-Silica Fume Concrete Wearing Course and Bridge Barrier Rails to update this historic bridge.
Owner: MnDOT
Location: Minneapolis, MN
Prime Contractor: Ames Construction Inc.
Contract Value: $2,141,108
PCiRoads poured this project with our new bridge deck paver as well as our new bridge deck sidewalk paver. PCiRoads work was consolidated at the end of the project, when schedule and logistics were particularly challenging with multiple contractors onsite trying to complete their work at once. PCiRoads expertise and resources helped seamlessly complete the project.